Ecco III Enterprises, Inc. was hired by the New York State Department of Transportation to completely rebuild two bridges located along the Saw Mill River Parkway (MSRP) in the village of Pleasantville, New York. The structures are under the historical arch bridges in Bedford Road, Pleasantville Road and Saw Mill
River. Historic bridges vault will not be affected by the reconstruction. two turnoffs be carried out during the construction of this project:
July 1 (2016), 21: 00-6: 00 (Sunday night through Thursday night). NIGHT ONLY.
MSRP completely closed and tra fi c target Grant Street / Marble Avenue Corridor.
Summer diversion: 21 consecutive days occurred between July 10 and August 26 (2016), 24 hours a day, 7 days a week. Traf fi c MSRP reduced to one lane in each direction, it moves in both northbound lanes.