Question No 6:

The scheduler should assign work plans for the crew to execute what percentage of the forecasted hours?

A. 100% to fill all available forecasted hours
B. More than 100% in case some jobs do not take as long
C. Less than 100% to allow for emergencies or breaks
D. It does not matter how much is scheduled

Answer: A